Pre-construction phase
The term ‘construction’ refers to the process of building something such as a house, bridge, tunnel, and so on.
Construction projects are typically divided up into stages, at the end of which the client assesses the state of development of the project and considers; whether it satisfies their strategic objectives, that it is affordable, that value is being delivered, and that risks are acceptable. They can then decide whether to progress to the next stage.
A typical project might follow stages such as:
- Stage 1: Business justification.
- Stage 2: Feasibility studies.
- Stage 3: Project brief.
- Stage 4: Concept design.
- Stage 5: Detailed design.
- Stage 6: Production information.
- Stage 7: Tender.
- Stage 8: Mobilisation.
- Stage 9: Construction.
- Stage 10: Occupation and defects liability period.
- Stage 11: Post occupancy evaluation.
Typically, the construction phase consists of carrying out the construction works described in the contract and preparing for the client to occupy the works.
The pre-construction works, in their broadest sense, might include any activities before the construction phase commences, such as; business planning, appointing consultants, the preparation of feasibility studies and options appraisals, preparing the project brief, designing the project, obtaining permissions, appointing a contractor, preparing for construction to commence and so on.
However, a specific legal meaning of “pre-construction phase” exists in relation to health and safety. The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced. They were introduced in 1994 following publication of European Directive 92/57/EEC on minimum safety and health standards for temporary or mobile construction sites.
The CDM Regulations 2015 suggests that the construction phase means the period of time beginning when construction work in a project starts and ending when construction work in that project is completed. The pre-construction phase refers to any period of time during which design or preparatory work is carried out for a project and may continue during the construction phase.
This might include:
- Appointing duty holders.
- Ensuring risks are eliminated or controlled through design work.
- Passing information to the principal contractor.
- Ensuring cooperation and coordination.
- Ensuring designers comply with their duties.
- Preparing pre-construction information.
For more information see: CDM 20215.
These activities may continue after the construction phase has commenced, as the design may continue to develop and so health and safety considerations may change.
NB Using Two Stage Open Book and Supply Chain Collaboration, published by HMSO in 2014, defines the preconstruction phase as: ‘…the phase of a project or programme of work before the Client authorises commencement of all works and related activities on and off site.’ It defines a preconstruction phase timetable as: ‘…a contractually binding timetable governing deadlines and interfaces for Preconstruction Phase activities by Integrated Team members under a Conditional Contract.’
[edit] Related articles on Designing Buildings
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February